EAC Realism - (|Structure|StruDesc|) ((|Unit|UnitName|)) | |
Project Officer: (|Element|ProjOff|) |
Element Code: (|Element|WbsNum|) |
Method 1 - Comparison of CV to VAC | |
Cum Cost Variance | (|CvCum|(-0)|[z1]|) |
VAC | (|Vac|(-0)|[n1]|) |
Method 2 - Comparison of CPI to TCPI-EAC | |
CPI | (|CpiCum|(-0)|([z3])|) |
TCPI-EAC |
(|TcpiLre|(-0)|([z3])|) |
Comparison of CPI to TCPI-EAC | (|CpiToLre|(-0)|([z3])|) |
Method 3 - Compare EAC to Calculated Forecasts | |
Contractor's EAC | (|Lre|([z1])|) |
wInsight Independent Calculated Forecasts | |
|
(|MovAvg3|([z1])|) |
|
(|MovAvg6|([z1])|) |
|
(|CumCpiFc|([z1])|) |
|
(|WtCostSch|([z1])|) |
|
(|Micom|([z1])|) |
|
(|CpiSpi|([z1])|) |
Cumulative Performance | |
|
(|CpiCum|([z1])|) |
|
(|SpiCum|([z1])|) |
Compare the EAC to range of statistical EACs. If the EAC is outside the range of calculated EACs, it will be flagged as optimistic or conservative. |
Review past performance efficiencies, Cum CPI and Cum SPI. These are used to calculate the calculated EACs. |
|
Method 4 - Compare EAC to Regression Forecasts |
|
Contractor's EAC | (|Lre|([z1])|) |
Linear Regression | (|LinRegr|([z1])|) |
Evaluate the EAC against the linear regression formula. Note that this is not a curvilinear function, but a straight line projection. | |
Notes | |
Weights for Cost + Schedule Forecast: Cost =
Schedule =
|